TRANSIT PROJECT ASSESSMENT PROCESS (TPAP) SCHEDULE
KEY MILESTONE |
DATE |
---|---|
Pre-TPAP Phase |
May 2017 to April 2020 |
Notice of Commencement of TPAP (120-day period) |
April 16, 2020 |
Notice of Completion of Environmental Project Report (EPR)/EPR Available for Review |
August 13, 2020 |
Agency/Stakeholder and Public Review Period (30 days): |
August 13, 2020 to September 11, 2020 |
Minister of the Environment, Conservation and Park's Decision (35 days): |
September 11, 2020 to October 15, 2020 |